Construction Cost Estimator: Hotel, School and Office Rates per ft²
Select a hotel, school or low-rise office reference and apply its rate to matching floor area. Different models and years are not a like-for-like price ranking.
Who it's for: architects, owners, and estimators who need to apply a published reference or their own dated construction rate using transparent arithmetic — not a market forecast — for a specific quantity and allowance set, at feasibility or schematic design.
Published building-cost references per m² or ft²
Choose a published reference, enter matching floor area, and calculate. Source facts travel with the result; you do not need to retype them.
Compare published rates and source details
Approximate published-reference total
Result, source and assumptions to copy
Reference arithmetic, not a project budget. No current-price adjustment, currency conversion or extra allowance is applied. A rate's cost inclusions remain those of its source.
Have a project-specific rate or additional allowances? Use the separate manual calculation.
—
Published area rates and sources
| Reference and period | Published / ft² | Converted / m² |
|---|---|---|
| 15-story hotel — U.S. national average (2025)2025 source column | USD 261.76 | ≈ USD 2,817.56 |
| Elementary school — U.S. national model (2024)2024 source table | USD 239.21 | ≈ USD 2,574.84 |
| 2–4-story office — published model endpoints2026 guide; underlying cost period not independently establishedSource size context: the selected source row covers 4,250–92,000 ft². This is source context, not a validated calculation limit. | USD 247.00 to USD 498.00 | ≈ USD 2,658.69 to USD 5,360.43 |
Method, source scope and period
1 ft² = 0.09290304 m². Divide a USD/ft² rate by this factor for USD/m². Divide m² area by the same factor before multiplying by the original rate. Only displayed values are rounded.
NIST area conversion definition. Unit conversion does not reconcile gross, net, finished or rentable area definitions.
15-story hotel — U.S. national average (2025)
15-story hotel construction model. Complete cost inclusions are not itemized; this is not a total-development budget. Use floor area measured on the source model basis. Gross, net and rentable areas are not interchangeable. No other hotel height, service tier or location is inferred. Room-based HVS development costs are a separate task.
Gordian / BD+C: Hotel construction costs for 2025 · publication date: 2025-04-17 · period: 2025 source column.
Elementary school — U.S. national model (2024)
U.S. national school-model averages with green-building considerations; detailed cost inclusions are not itemized. Use floor area measured on the source model basis. Gross, net and rentable areas are not interchangeable. These are historical models, not 2026 quotes. Universities, seat counts and local premiums are not inferred.
Gordian / BD+C: K-12 school construction costs for 2024 · publication date: 2024-02-22 · period: 2024 source table. Re-read 2026-10-12.
2–4-story office — published model endpoints
Published construction-model reference; a complete breakdown of cost inclusions is not provided in this article. Use floor area measured on the source model basis. Gross, net and rentable areas are not interchangeable. The page also retains a 2025 heading. This 2–4-story model is not an office fit-out rate, local quote or complete development budget.Source size context: the selected source row covers 4,250–92,000 ft². This is source context, not a validated calculation limit.
Gordian RSMeans: Cost to build an office · publication date: 2026-05-29 · period: 2026 guide; underlying cost period not independently established.
Selected figures read 2026-09-11. That check date is not a cost observation date. Missing inclusions remain unknown, not excluded; do not automatically add land, fees, FF&E, taxes or contingency.
Two source endpoints are separate scenarios, not a statistical interval. No bed, seat or room count is converted to area.
Published benchmarks
Hard construction cost per square foot by building type from one published matrix (RLB, Chicago), and average construction cost per square metre for the ten most expensive cities worldwide (Turner & Townsend). Pick a row to use it as the entered rate, or enter your own market’s figure.
| Benchmark | Value | Unit | Edition | Scope | Source | |
|---|---|---|---|---|---|---|
| Warehouse (industrial) | 155–245 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Office, prime | 355–580 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Office, secondary | 215–350 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Retail, shopping center | 220–465 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Retail, strip | 170–280 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Multi-family residential | 220–490 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Single-family residential | 285–570 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Elementary school | 320–480 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| High school | 375–515 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| University | 450–910 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Hotel, 3-star | 385–515 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Hotel, 5-star | 530–810 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Hospital, general | 455–925 | $/sf | Q1 2026 | Chicago, IL | RLB Quarterly Construction Cost Report, North America, Q1 2026 | |
| Average construction cost, New York City | 5,744 | $/m² | International Construction Market Survey, latest | New York, NY | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, San Francisco | 5,504 | $/m² | International Construction Market Survey, latest | San Francisco, CA | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Zurich | 5,386 | $/m² | International Construction Market Survey, latest | Zurich, CH | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Geneva | 5,386 | $/m² | International Construction Market Survey, latest | Geneva, CH | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, London | 5,385 | $/m² | International Construction Market Survey, latest | London, UK | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Los Angeles | 4,786 | $/m² | International Construction Market Survey, latest | Los Angeles, CA | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Chicago | 4,695 | $/m² | International Construction Market Survey, latest | Chicago, IL | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Tokyo | 4,647 | $/m² | International Construction Market Survey, latest | Tokyo, JP | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Philadelphia | 4,604 | $/m² | International Construction Market Survey, latest | Philadelphia, PA | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
| Average construction cost, Sapporo | 4,577 | $/m² | International Construction Market Survey, latest | Sapporo, JP | Turner & Townsend, US cities most expensive places to build globally | Reference only — enter a verified rate separately |
Each button selects the stated displayed value, not a typical rate, statistical confidence interval, or recommendation. Inequality bounds are reference-only. Figures are as published on the linked page; check edition, unit, scope and what the rate includes before using one. When a base-date field is present, enter its verified date yourself; a publication year is not a benchmark base month.
How to use this calculator
The formula
Worked example
When this estimate will be off
- The thirteen RLB rows are all Chicago-only — comparing building types here does not compare cities; comparing cities requires switching to the Turner & Townsend rows instead.
- Turner & Townsend rows are one blended average per city, not split by building type, and are priced per square metre, not per square foot.
- Benchmark rows on this page are sourced reference points, not market data for your project; no currency conversion is supplied.
- No cost-plan, procurement, escalation, tax, finance, schedule, risk, or professional adequacy determination is made.
Frequently asked questions
Yes. Choose one of the published area references above and enter floor area in m² or ft². Its source, period and scope stay attached to the result. No unlisted model, local premium, current-price adjustment or complete project budget is inferred.
No. Room, bed and seat counts are not areas. Only the published area-reference form converts m² and ft², preserving the same area. The separate manual form needs a quantity and rate already expressed in matching units; no currency conversion is performed.
No. It applies transparent arithmetic to a user-supplied benchmark and allowances — it does not predict bids, escalation, or final cost.
Use a dated source for the same market, currency, measurement basis, scope, and project type as the construction project you're estimating. The benchmark table above lists sourced reference points, not market data for your project.
So nothing already included in the base rate is counted twice. Enter only allowances not already reflected in the benchmark rate itself.
Only to the extent those costs are already included in your verified base rate or explicit additional allowances. This worksheet does not separately derive or validate escalation, taxes, finance, procurement risk, or professional adequacy.
Sources
- User-identified cost source — must provide the rate, market, date, currency, measurement basis, scope, inclusions and exclusions
This free Construction Cost Estimator is built and maintained by DataDrivenAEC, using the relevant codes and standards. It does not substitute for professional judgment.