AEC workflow

Estimate & Procure

Move from an early cost or product question to a documented estimate, comparison, or procurement decision.

Follow the process

How to build a reviewable construction cost estimate

Start with the decision the estimate needs to support, then establish quantities and comparable rates before adding allowances. This six-step working guide helps you produce a traceable early-stage scenario; the individual calculators and software records below support particular steps rather than replacing the whole process.

Your deliverable: A basis-of-estimate record, traceable quantities and rates, a reconciled cost scenario, and an open-questions list with owners and the next review date.

Skip to the resource library ↓

Before you start

  • A project brief, estimate purpose and decision date, plus the current drawing or model revision.
  • A defined measurement basis and quantities, or a record of which quantities still need to be established.
  • An identifiable rate source with its market, currency, base period and cost inclusions, or a plan to obtain one.
  • A named estimate preparer and reviewer, with authority to resolve scope and assumptions.
  1. Define the estimate basis

    Inputs
    Project brief, estimate purpose, location, project stage and latest design information.
    Action
    Write down what the estimate includes before choosing a tool. Separate construction work from land, fit-out, equipment and wider development costs. Name the currency, measurement convention and decision the estimate will inform.
    Output
    A basis-of-estimate record with included work, exclusions, design revision and unresolved assumptions.
    Review checkpoint
    Can another team member tell what is being estimated and what is outside the total?
    Common mistake
    Starting with a cost-per-area figure and treating it as a complete project budget.

    Resources for this step

  2. Establish quantities and measurement basis

    Inputs
    The same drawing or model revision, measurement convention and scope agreed in step 1.
    Action
    Choose a quantity that matches the intended rate: floor area for a rate per area, key count for a rate per hotel key, or measured work items for a detailed takeoff. Record how each quantity was measured and reconcile totals before pricing it.
    Output
    A quantity schedule carrying units, measurement definitions, revision and source references.
    Review checkpoint
    Do the quantity and rate denominators describe the same thing, including the area definition?
    Common mistake
    Multiplying a per-key rate by floor area, or mixing net and gross areas without reconciliation.

    Resources for this step

  3. Select comparable, dated rates

    Inputs
    Quantity schedule and an identifiable benchmark, cost database or quotation.
    Action
    Read the rate source, not just the number. Compare building subtype, location, currency, observation period, unit and included work. Keep a survey edition separate from the base period of the underlying costs. Document any adjustment instead of silently applying a generic factor.
    Output
    A rate-selection record linking the chosen value or range to its source and cost scope.
    Review checkpoint
    Is the rate comparable to this quantity and project scope? If that is unknown, obtain clarification before using it as a project estimate.
    Common mistake
    Using a development-cost benchmark as a hard-construction rate, or inventing a base month from a publication year.

    Resources for this step

  4. Build the base estimate

    Inputs
    Reconciled quantities and comparable rates with their source records.
    Action
    Multiply each quantity by its matching rate and retain the calculation basis. Use a single-rate scenario only for an appropriately bounded question; a multi-package estimate needs its own quantity and rate breakdown. Compare alternatives on the same scope before interpreting a difference.
    Output
    A traceable base amount or itemized base estimate, with each source and assumption retained.
    Review checkpoint
    Can the reviewer reproduce the arithmetic without guessing units, scope or source identity?
    Common mistake
    Treating a correctly multiplied number as proof that the rate or project scope is correct.

    Resources for this step

    • Construction cost estimator

      Apply an entered quantity and rate for a bounded scenario; this is not an automatic market-price database or detailed bill of quantities.

  5. Reconcile allowances without double counting

    Inputs
    Base estimate, source inclusions, project risks and separately justified allowances.
    Action
    For each fee, contingency or other allowance, first ask whether it is already in the base rate. State its amount or percentage and the base it applies to. Handle escalation, taxes, finance and other development costs explicitly in the appropriate cost plan rather than assuming they have been derived by a simple calculator.
    Output
    A reconciled scenario with base cost, each additional allowance and remaining exclusions visible.
    Review checkpoint
    Is every added item justified, non-overlapping and calculated on the intended base?
    Common mistake
    Adding fees twice because the selected benchmark already includes them, or compounding percentages without stating that method.

    Resources for this step

  6. Review, hand over and define the next update

    Inputs
    Basis record, quantities, rates, arithmetic, allowances and unresolved questions.
    Action
    Ask the named reviewer to challenge comparability and completeness as well as the arithmetic. Hand over the assumptions and sources with the number, assign owners to unresolved questions, and record which design, procurement or source change will trigger the next estimate revision.
    Output
    A versioned estimate package and decision record, with review status and the next action clearly stated.
    Review checkpoint
    Does the recipient know what this scenario can support, what remains unverified and who updates it?
    Common mistake
    Sending only the total, then reusing it after the scope or source has changed.

    Resources for this step

Worked journey: an illustrative early-stage scenario

Synthetic training example only: neither the rate nor the allowances below are published market guidance or a recommended budget. Assume the example rate excludes the stated additions; real work requires source and scope verification.

Basis
Compare one explicitly defined construction-work scope. Keep land, finance and tax outside this example and record those exclusions.
Quantities
Use 1,000 m² measured on the same stated area basis as the example rate.
Rates
For demonstration only, use USD 2,000/m². This invented teaching value has no verified market, observation period or project applicability.
Base estimate
1,000 m² × USD 2,000/m² = USD 2,000,000.
Allowances
Illustrative additions on the base: fees 10% = USD 200,000; contingency 5% = USD 100,000; other 3% = USD 60,000. Total = USD 2,360,000; these additions are not compounded.
Handover
Retain all inputs and exclusions. The arithmetic is reproducible, but this teaching scenario is not ready for a project decision until real comparable inputs and responsible review replace its assumptions.

Basis-of-estimate checklist

Select and copy the checklist into your project document. Complete it there; this page does not save project information.

Continue to the resource library ↓

Back to the estimating process ↑

70 connected resources

Explore this workflow

AEC technology profiles connected to this workflow.

Workflow pick

Beam AI

AI takeoff with human QA

Open resource →
Workflow pick

Kreo Software

AI-powered construction takeoff and estimating platform

Open resource →
Workflow pick

Togal.AI

AI-powered construction takeoff and pre-construction automation

Open resource →

1build

The API for live, county-level U.S. construction cost data

Open resource →

Archdesk

All-in-one cloud construction management platform

Open resource →

ArcSite

Mobile on-site drawing, material takeoff, and estimating for specialty contractors

Open resource →

Attentive.ai (Beam AI)

AI-powered construction takeoff and estimating software for GCs, subcontractors, and suppliers

Open resource →

Builda Price

Job-costing and quoting platform for New Zealand builders

Open resource →

Buildertrend

Cloud-based construction project management for builders, remodelers, and contractors

Open resource →

Buildxact

Residential construction estimating and project management platform

Open resource →

Clearstory

Real-time change order and T&M tracking platform for construction teams

Open resource →

Concrete Cost Estimator

Calculate total project cost including materials, labor, and delivery

Open resource →
Browse technology directory →

A human decision first

Being data-driven goes beyond technology

It starts with good questions, trusted evidence, and clear decisions.

Book a conversation →